Pembangunan Jalur Pedestrian di Daan Mogot Mencapai 54 Persen

Daan Mogot Pedestrian Arrangement Has Touched 54 Percent

We're optimistic that the project can finish on time

Progress of structuring the 1.7-kilometer length pedestrian track on Jalan Daan Mogot, West Jakarta, has so far reached 54 percent. It is expected that the project can be complete by the end of this year.

JPO's Iron Buffer on Jl. Daan Mogot Evacuated After Being Hit By Truck

West Jakarta Bina Marga Sub-dept. Head, Riswan Efendi said, his sub-dept. keeps optimizing the project.

"We're optimistic that the project can finish on time," he expressed, Friday (10/6).

He added the pedestrian would have park, bike track, disability steering tiles, park bench and good drainage.

"It's carried out along with related unit related to the main tasks and functions (tupoksi) For instance, park arrangement becomes the responsible of Forestry Sub-dept. and so on," he closed.

Linked News
Popular News indeks
  1. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye790 personTiyo Surya Sakti
  2. Pramono Calls for Enhanced Synergy at DPRD Post-Eid Gathering

    access_time30-03-2026 remove_red_eye697 personDessy Suciati
  3. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye636 personTiyo Surya Sakti
  4. Kampung Rambutan Terminal Sees Increase in Intercity Bus Passengers

    access_time03-04-2026 remove_red_eye545 personNurito
  5. Gov Pramono: Jakarta Prepared to Adopt Weekly WFH Scheme

    access_time30-03-2026 remove_red_eye444 personDessy Suciati
KONTAK KAMI
Berita Jakarta Berita Jakarta TV

Jl. Medan Merdeka Selatan 8-9 Blok F Lt. II Jakarta
local_phone +62 21 3822356
email redaksi@beritajakarta.id

TAUTAN LAINNYA
Tentang Kami | Sitemap | Infografis

© copyright 2001 - 2026 All Rights Reserved