Pembangunan Jalur Pedestrian di Daan Mogot Mencapai 54 Persen

Daan Mogot Pedestrian Arrangement Has Touched 54 Percent

We're optimistic that the project can finish on time

Progress of structuring the 1.7-kilometer length pedestrian track on Jalan Daan Mogot, West Jakarta, has so far reached 54 percent. It is expected that the project can be complete by the end of this year.

JPO's Iron Buffer on Jl. Daan Mogot Evacuated After Being Hit By Truck

West Jakarta Bina Marga Sub-dept. Head, Riswan Efendi said, his sub-dept. keeps optimizing the project.

"We're optimistic that the project can finish on time," he expressed, Friday (10/6).

He added the pedestrian would have park, bike track, disability steering tiles, park bench and good drainage.

"It's carried out along with related unit related to the main tasks and functions (tupoksi) For instance, park arrangement becomes the responsible of Forestry Sub-dept. and so on," he closed.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye869 personTiyo Surya Sakti
  2. TransJabodetabek Expansion, a Strategic Step to Increase Public Transportation Use

    access_time26-01-2026 remove_red_eye428 personFakhrizal Fakhri
  3. South Jakarta Tackles 38 Dengue Cases to Prevent Outbreak

    access_time02-02-2026 remove_red_eye403 personTiyo Surya Sakti
  4. Jakarta Prepares OMC and 200 Excavators to Prevent Flood

    access_time26-01-2026 remove_red_eye371 personDessy Suciati
  5. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye359 personDessy Suciati
KONTAK KAMI

Jl. Medan Merdeka Selatan 8-9 Blok F Lt. II Jakarta
local_phone +62 21 3822356
email redaksi@beritajakarta.id

TAUTAN LAINNYA
Tentang Kami | Sitemap | Infografis

© copyright 2001 - 2026 All Rights Reserved

close