Pembangunan Jalur Pedestrian di Daan Mogot Mencapai 54 Persen

Daan Mogot Pedestrian Arrangement Has Touched 54 Percent

We're optimistic that the project can finish on time

Progress of structuring the 1.7-kilometer length pedestrian track on Jalan Daan Mogot, West Jakarta, has so far reached 54 percent. It is expected that the project can be complete by the end of this year.

JPO's Iron Buffer on Jl. Daan Mogot Evacuated After Being Hit By Truck

West Jakarta Bina Marga Sub-dept. Head, Riswan Efendi said, his sub-dept. keeps optimizing the project.

"We're optimistic that the project can finish on time," he expressed, Friday (10/6).

He added the pedestrian would have park, bike track, disability steering tiles, park bench and good drainage.

"It's carried out along with related unit related to the main tasks and functions (tupoksi) For instance, park arrangement becomes the responsible of Forestry Sub-dept. and so on," he closed.

Linked News
Popular News indeks
  1. Nighttime Surveillance on Railroad Banks of Jalan I Gusti Ngurah Rai Intensified

    access_time08-05-2026 remove_red_eye2632 personNurito
  2. Closure of Railway Level Crossings Socialized

    access_time13-05-2026 remove_red_eye2335 personTiyo Surya Sakti
  3. Governor Pram Appreciates Residents for Keeping Jakarta Safe and Comfortable

    access_time09-05-2026 remove_red_eye973 personFolmer
  4. Waste Sorting Movement Boosts Circular Economy

    access_time12-05-2026 remove_red_eye834 personFakhrizal Fakhri
  5. Fire Burns Five Houses in Cengkareng Extinguished

    access_time12-05-2026 remove_red_eye733 personBudhi Firmansyah Surapati
KONTAK KAMI
Berita Jakarta Berita Jakarta TV

Jl. Medan Merdeka Selatan 8-9 Blok F Lt. II Jakarta
local_phone +62 21 3822356
email redaksi@beritajakarta.id

TAUTAN LAINNYA
Tentang Kami | Sitemap | Infografis

© copyright 2001 - 2026 All Rights Reserved